IREN Limited

A former bitcoin miner turning its power-hungry sites into data centres, filling them with NVIDIA's chips and renting them to AI labs under contracts lasting years.

Our viewNeutral Medium conviction
The scores
The profile · 1-4
Growth3/4 ↑

AI Cloud revenue grew eightfold and $4B of run-rate is signed, but June-quarter revenue fell as mining stopped; a two-year record.

Business quality2/4 →

Owned power and rising prices in a shortage, but an outside rater ranks its managed cloud bottom and the GPUs are the same everyone rents.

Financial position2/4 ↓

Cash roughly matches debt, but next year's plan needs $3B to $8B not yet raised, and the newest GPU debt costs 9% over 30 months.

Execution record2/4 →

Signed Microsoft and NVIDIA and delivered Horizon 1, but late on NVIDIA supply, and users report outages at the older sites.

Per share capture1/4 ↓

Revenue rose 41% while revenue per share stood still; next year's build may need as many new shares again, and founders' grants vest on time.

Potential3/4 ↑

A bounded upside substantially committed: $4B contracted and largely funded, on power already granted, with 2027 still unsold.

Risk profile2/4 →

Microsoft and NVIDIA are most of the contracted revenue, and three Microsoft tranches can each be ended in one step if late.

Valuation3/4 ↑

At about 3 times the contracted run-rate, the price pays for the 2026 contracts roughly as described and little for the 2027 build.

Evidence quality3/4 →

Revenue, contracts and debt are filed, but deal prices and the run-rate are management's word, and no counterparty names IREN.

The bet · 2-3 years
Speculation2.3×

If it works 2.3× · if it fails you keep up to 55%.

The Verdict

We rate IREN neutral. It owns sites with scarce grid power and rents NVIDIA's chips in them to AI labs, but the business is weak for now: Microsoft and NVIDIA have signed, yet an outside rater calls its older sites the industry's worst and growth is paid for in new shares. The price is fair for the contracts already signed and pays little for what comes after. As a bet it is speculative: if the next build is sold and funded mostly with debt, the shares could be worth about twice today's; if it stalls, shareholders keep at most about half. It turns on who pays for next year's build.

The long casePower for AI computing is scarcer than chips, and IREN already holds the grid connections, so it can rent GPUs to labs if it can fund the building.

The evidence under this - 10 claims
C04facthigh confidence
IREN holds grid connections for about 5 GW across Texas, British Columbia, Oklahoma, South Australia and Spain, of which Childress is 750 MW and the two Sweetwater sites 2 GW.
against this

A grid agreement is not energised capacity: Sweetwater 1's first building and substation are still under construction, and Kiowa, Bundey and Badajoz are 2028 projects.

current state · 2026-08-27written 2026-10-18
C07facthigh confidence
Microsoft's five-year, about $9.7B agreement covers four 50 MW liquid-cooled tranches at Childress; Horizons 2 to 4 are due in the December 2026 quarter with grace periods to early Q2 2027, and Microsoft may end a late tranche.
against this

Horizon 1 itself was late, delayed by NVIDIA component shortages, and if a funded tranche ends without a new customer IREN guarantees that tranche's GPU debt.

current state · 2026-08-27written 2026-10-18
C08facthigh confidence
NVIDIA signed a five-year, about $3.4B cloud contract in May 2026, served on about $1.6B of Dell servers; with Microsoft's it is a substantial majority of contracted revenue.
against this

NVIDIA is also the sole GPU supplier and holds a right to invest up to $2.1B in IREN shares, so its contract is not an arm's-length test of demand.

current state · 2026-08-27written 2026-10-18
C11facthigh confidence
SemiAnalysis rated IREN's cloud Not Recommended in September 2026, calling its British Columbia capacity the worst site in the industry according to users, while saying Childress and Sweetwater look much better and that its bare-metal rentals meet plenty of demand.
against this
  • Microsoft accepted Horizon 1 at Childress and NVIDIA certified it as an Exemplar Cloud, so the largest buyers' own tests passed where the rating is worst.
  • SemiAnalysis sells consulting to GPU clouds and their buyers; it is independent of IREN but not of the market it rates.
current state · 2026-09-23written 2026-10-18
C29estimatemedium confidence
At $26.99 on about 393.5M shares the market value is $10.6B and the vendor's company value $12.6B: about 3.1 times the more than $4B of run-rate contracted for 2026, and 17.8 times trailing sales.
derivedthe pack's market value and company value (S23), divided by the $4B contracted run-rate in C05 and by FY26 revenue in C02
against this
  • The company value uses June 30 net debt; September-quarter spending will have raised it.
  • About $3B of the $4B was not yet billing, so the multiple on revenue actually earned is far higher.
current state · 2026-10-16written 2026-10-18
C30inferencemedium confidence
The price pays for the 2026 contracts and treats the 2027 build mostly as a funding risk: at about 3 times contracted run-rate against Nebius's roughly 9 times its own, the market expects the next gigawatt to cost shareholders.
derivedC29's 3.1 times against the cohort's 9.9 times trailing median (C31) and Nebius's 9 times guided run-rate; the FY27 capex in C19 is more than twice the market value, and the 41% share growth in C22 shows who paid for the last year
against this
  • Nebius's run-rate is mostly billing already, while three quarters of IREN's $4B is still to be delivered, so part of the discount is delivery risk rather than funding.
  • Analysts' $7.28B for fiscal 2028 at the cohort's lowest multiple would be worth more than twice today's company value, so the price may assume less than the plan.
forwardwritten 2026-10-18
C28factmedium confidence
Analysts' average forecasts put revenue at $2.72B for the year to June 2027, $7.28B for 2028 and $13.2B for 2029, the later years from a panel of about four, against $707.0M filed for FY2026.
against this

Four analysts is a thin base, and the 2028 figure needs about 550 MW of IT load billing, more than the 300 MW due in 2026.

forwardwritten 2026-10-18
C53estimatelow confidence
If the build stalls with the 2026 contracts billing, IREN's net debt would be about $9B once that capacity is paid for, against about $1.9B at June 30.
derivedJune 30 net debt of $1.9B (C18, C29) plus roughly $7B of the FY27 spending tied to 2026 deliveries net of prepayments, funded with GPU debt (C19, C20)
against this

Management has not split the $25B to $30B between 2026 deliveries and 2027 builds, so the $7B is this thesis's figure.

forwardwritten 2026-10-18
C19management claimhigh confidence
Management guides FY27 capital spending of about $25B to $30B, against about $14B of cash, committed GPU financing and prepayments, a further $8B of GPU financing and prepayments targeted, and the rest from data-centre financing, operating cash and corporate sources.
against this
  • The rest, roughly $3B to $8B, has no named source, and corporate sources include new shares and convertibles.
  • The data centres are all unencumbered today, so asset finance against them could fill much of the gap without equity.
forwardwritten 2026-10-18
C46estimatemedium confidence
Funding the FY27 plan likely needs several billion dollars beyond what is arranged: if half of a $3B to $8B gap came as shares at $26.99, that is about 55M to 150M new shares, 14% to 38% more.
derivedC19's $25B to $30B less $14B in hand and $8B targeted leaves $3B to $8B; half of it in shares at the October 16 close of $26.99 on C29's 393.5M shares
against this

Debt against the unencumbered data centres could fund all of it, and higher prepayments on new deals have exceeded GPU cost before.

forwardwritten 2026-10-18
01

The company

IREN builds data centres on land it owns, connected to grid power it secured while it was a bitcoin miner, and fills them with racks of NVIDIA's newest chips. AI labs and companies rent those chips, mostly as bare machines they run themselves, to train and run their models.

The alternatives are renting from Microsoft, Amazon, Google or another specialist, or building. About 40 MW was running AI work in June; Microsoft accepted IREN's first purpose-built hall in August, while an outside rater says older Canadian sites let users down.

The evidence under this - 4 claims
C01facthigh confidence
IREN builds and owns its data centres and rents NVIDIA GPU clusters in them to AI companies, from grid power to software; about 40 MW of AI cloud was running at June 30, 2026.
current state · 2026-06-30written 2026-10-18
C04facthigh confidence
IREN holds grid connections for about 5 GW across Texas, British Columbia, Oklahoma, South Australia and Spain, of which Childress is 750 MW and the two Sweetwater sites 2 GW.
against this

A grid agreement is not energised capacity: Sweetwater 1's first building and substation are still under construction, and Kiowa, Bundey and Badajoz are 2028 projects.

current state · 2026-08-27written 2026-10-18
C12facthigh confidence
Horizon 1 was delivered to and accepted by Microsoft in August 2026 and earned NVIDIA Exemplar Cloud status on GB300 NVL72 systems.
historical · August 2026written 2026-10-18
C11facthigh confidence
SemiAnalysis rated IREN's cloud Not Recommended in September 2026, calling its British Columbia capacity the worst site in the industry according to users, while saying Childress and Sweetwater look much better and that its bare-metal rentals meet plenty of demand.
against this
  • Microsoft accepted Horizon 1 at Childress and NVIDIA certified it as an Exemplar Cloud, so the largest buyers' own tests passed where the rating is worst.
  • SemiAnalysis sells consulting to GPU clouds and their buyers; it is independent of IREN but not of the market it rates.
current state · 2026-09-23written 2026-10-18

How it makes money

A customer signs for a block of chips for three to five years, pays a large share up front, and then pays monthly whether it uses them or not. IREN borrows against each contract to buy the chips, so the prepayment and the loan cover most of the cost. Bitcoin mining still brought in most of last year's revenue, and it ends in December.

The evidence under this - 5 claims
C06management claimmedium confidence
Recent three-year contracts price above $20M a year per megawatt of IT load with about a two-year payback, three-year pricing is up about 125% since November, and prepayments fund 45% to 55% of the GPUs.
against this
  • The payback is stated on management's own costs for capacity not yet running; no customer has published a price.
  • The Microsoft contract, the largest, works out near $10M a year per megawatt of its 200 MW, so the blended book is well below the recent-deal figure.
current state · 2026-08-27written 2026-10-18
C09facthigh confidence
July's $2.8B of new contracts lifted the year-end run-rate target from $3.7B to over $4B, about 85% then signed, at about 45% prepaid over a four-year average term, for customers from Microsoft and NVIDIA to Perplexity, Figure AI and Together AI.
current state · 2026-07-20written 2026-10-18
C20facthigh confidence
GPU debt is cheaper where the buyer is investment grade: $3.6B for the Microsoft GPUs at about 6% to 2031, against $2.4B at a fixed 9% for Mackenzie in August, repaid 30 months after each draw.
current state · 2026-08-27written 2026-10-18
C02facthigh confidence
FY26 revenue was $707.0M: AI Cloud $128.8M, up from $16.4M, and bitcoin mining $578.2M.
against this

AI Cloud was still 18% of the year's revenue; the fourth quarter's $70.5M was the first quarter it approached half.

historical · FY2026 (year to June 30, 2026)written 2026-10-18
C03management claimhigh confidence
Bitcoin mining, 23.2 EH/s on about 380 MW, is being switched off to free power for GPUs and should be effectively gone by the end of December 2026.
against this

Mining still earned $578.2M in FY26 and its margin funded the build; switching it off before GPUs bill leaves quarters like June's, when revenue fell 27% on a year earlier.

forwardwritten 2026-10-18
Where the money comes from, stream by stream
StreamShare of sales (FY2026)How it earns it
Bitcoin mining81.8%Mining bitcoin with its own machines on its own power, paid in bitcoin; being switched off by December 2026.
AI Cloud Services18.2%Renting NVIDIA GPU clusters to AI labs and companies, mostly under multi-year prepaid contracts; about half of revenue by the June quarter.

Who runs it

Brothers Daniel and William Roberts founded IREN in 2018 and run it together as co-chief executives. They own about 3% of the shares each, but special shares give each almost a fifth of the votes. In June each received restricted shares valued at $275.9M that vest with time alone, with no performance test. Their yearly share awards depend on beating the Russell 2000 index; no award rides on sales, profit or returns.

The evidence under this - 3 claims
C40facthigh confidence
Co-founders Daniel and William Roberts each hold 13.19M shares, 3.2%, and through one B Class share each 19.8% of the votes; directors and officers hold 6.7% of shares and 39.7% of votes.
current state · 2026-09-28written 2026-10-18
C41facthigh confidence
In June 2026 each co-chief executive received a Staking Grant of 9.10M time-vesting restricted shares valued at $275.9M, vesting over four years with a two-year hold and no further grants before FY2031.
against this

The board presents the grant as replacing five years of annual awards, so the yearly cost is lower than the headline suggests.

historical · June 2026written 2026-10-18
C42facthigh confidence
Annual performance shares vest on IREN's total return against the Russell 2000 over three years; short-term bonuses rest on safety, an operating scorecard and group and personal goals at the board's discretion.
current state · 2026-10-13written 2026-10-18
02

Why it wins, and who could beat it

Why customers come back

In AI computing the shortage is not chips but power: a new data centre can wait years for a grid connection, and British Columbia and Texas are now rationing or reviewing new ones. IREN already holds about 5 GW of connections.

That shows up in prices. Management says three-year contract prices more than doubled since November and recent deals pay back the chips in about two years; Nebius, a rival, prices its deals at the same level, and an outside index of chip rents is still rising.

The evidence under this - 5 claims
C04facthigh confidence
IREN holds grid connections for about 5 GW across Texas, British Columbia, Oklahoma, South Australia and Spain, of which Childress is 750 MW and the two Sweetwater sites 2 GW.
against this

A grid agreement is not energised capacity: Sweetwater 1's first building and substation are still under construction, and Kiowa, Bundey and Badajoz are 2028 projects.

current state · 2026-08-27written 2026-10-18
C51facthigh confidence
British Columbia limits new data-centre power from February 2026, and Texas now reviews and can curtail large new loads, both in the 10-K's risk factors.
current state · 2026-08-27written 2026-10-18
C06management claimmedium confidence
Recent three-year contracts price above $20M a year per megawatt of IT load with about a two-year payback, three-year pricing is up about 125% since November, and prepayments fund 45% to 55% of the GPUs.
against this
  • The payback is stated on management's own costs for capacity not yet running; no customer has published a price.
  • The Microsoft contract, the largest, works out near $10M a year per megawatt of its 200 MW, so the blended book is well below the recent-deal figure.
current state · 2026-08-27written 2026-10-18
C14factmedium confidence
Nebius, the closest listed rival, also priced its Q2 2026 deals at $20M to $25M a year per megawatt with prepayments of 50% to 60%.
against this

Both figures are companies describing their own deals; no buyer has confirmed either.

current state · 2026-06-30written 2026-10-18
C13facthigh confidence
Silicon Data's neocloud H100 rental index read $2.82 an hour on October 17, 2026, up 6.4% in a week.
against this

The H100 is two generations old; IREN's contracts are on B200, B300 and GB300 systems the index does not track, so it shows the market's direction rather than IREN's prices.

current state · 2026-10-17written 2026-10-18

The threat

Bigger specialists sell the same thing: CoreWeave's backlog is many times IREN's, and Nebius is rated top tier where IREN is rated bottom. Google now sells its own chips, which Anthropic is buying. And Microsoft, IREN's largest customer, is building its own data centres too.

The evidence under this - 6 claims
C37facthigh confidence
Rival neoclouds are winning the same buyers: Nscale has up to $43.8B from Microsoft and $44.6B from Anthropic, and CoreWeave's backlog is more than ten times IREN's contracted run-rate.
current state · 2026-09-18written 2026-10-18
C32facthigh confidence
CoreWeave, the largest listed GPU cloud, held $103.7B of remaining contract obligations at June 30, 2026, while its adjusted operating margin fell to 5% from 16%.
against this

CoreWeave's margin fell partly because capacity comes online ahead of its revenue, which IREN's own 2027 ramp will repeat.

historical · Q2 2026written 2026-10-18
C14factmedium confidence
Nebius, the closest listed rival, also priced its Q2 2026 deals at $20M to $25M a year per megawatt with prepayments of 50% to 60%.
against this

Both figures are companies describing their own deals; no buyer has confirmed either.

current state · 2026-06-30written 2026-10-18
C11facthigh confidence
SemiAnalysis rated IREN's cloud Not Recommended in September 2026, calling its British Columbia capacity the worst site in the industry according to users, while saying Childress and Sweetwater look much better and that its bare-metal rentals meet plenty of demand.
against this
  • Microsoft accepted Horizon 1 at Childress and NVIDIA certified it as an Exemplar Cloud, so the largest buyers' own tests passed where the rating is worst.
  • SemiAnalysis sells consulting to GPU clouds and their buyers; it is independent of IREN but not of the market it rates.
current state · 2026-09-23written 2026-10-18
C35facthigh confidence
Anthropic signed for multiple gigawatts of Google TPU capacity from 2027, and Alphabet now sells TPU systems to outside customers.
against this

Anthropic also signed up to $44.6B with Nscale, which rents NVIDIA chips, so the move to TPUs adds a supplier rather than replacing one.

current state · 2026-06-30written 2026-10-18
C36facthigh confidence
The largest buyers also build: Microsoft has $329.1B of data-centre leases not yet started and Meta guides 2026 capex at $130B to $145B, while both still rent outside capacity.
against this

Meta says most of its $349.31B of commitments are third-party cloud capacity, so its own building has not stopped it renting.

current state · 2026-06-30written 2026-10-18

The rivals: CRWV, NBIS, GOOGL, MSFT, META, AMZN, ORCL, and 1 more that is private, in-house or listed abroad.

Who else does this, rival by rival
TickerRivalHow far alongPriced against it
CRWVCoreWeave, Inc.Priced against it: YesOn saleYes
NBISNebius Group N.V.Priced against it: YesOn saleYes
PrivateNscale, Crusoe and LambdaPriced against it: PrivateOn salePrivate
GOOGLGoogle TPU systems sold to outside customersPriced against it: YesOn saleYes
MSFT · METAMicrosoft's and Meta's own data-centre buildsPriced against it: YesOn saleYes
AMZNAmazon.comPriced against it: YesOn saleYes
ORCLOraclePriced against it: YesOn saleYes
03

How big it could get

How big this could get

Specialised AI clouds took in more than $25B in 2025, with $9B in the last quarter alone, up 223% on a year earlier. The International Energy Agency expects the electricity used by AI servers to grow about 30% a year to 2030. Nobody publishes how much capacity these clouds rent out, so the market can be bounded but not counted.

The evidence under this - 3 claims
C33facthigh confidence
Synergy Research measured specialised AI cloud revenue at more than $25B in 2025, $9B in Q4 alone, up 223% on a year earlier.
against this

Synergy's forecast of close to $400B by 2031 is a projection, not a measurement, and is not used here.

historical · 2025written 2026-10-18
C34facthigh confidence
The IEA projects data-centre electricity use more than doubling to about 945 TWh by 2030, with AI server consumption growing 30% a year.
against this

The IEA's own range runs from a lower efficiency case to a higher lift-off case; the base case is one scenario of several.

forwardwritten 2026-10-18
C32facthigh confidence
CoreWeave, the largest listed GPU cloud, held $103.7B of remaining contract obligations at June 30, 2026, while its adjusted operating margin fell to 5% from 16%.
against this

CoreWeave's margin fell partly because capacity comes online ahead of its revenue, which IREN's own 2027 ramp will repeat.

historical · Q2 2026written 2026-10-18

Who has signed

Microsoft signed about $9.7B over five years for four halls in Texas, and NVIDIA about $3.4B over five years; together they are most of what is contracted. Smaller labs such as Perplexity, Figure AI and Together AI fill the rest, and an unnamed frontier lab signed in August. None of the buyers has published its terms.

The evidence under this - 4 claims
C07facthigh confidence
Microsoft's five-year, about $9.7B agreement covers four 50 MW liquid-cooled tranches at Childress; Horizons 2 to 4 are due in the December 2026 quarter with grace periods to early Q2 2027, and Microsoft may end a late tranche.
against this

Horizon 1 itself was late, delayed by NVIDIA component shortages, and if a funded tranche ends without a new customer IREN guarantees that tranche's GPU debt.

current state · 2026-08-27written 2026-10-18
C08facthigh confidence
NVIDIA signed a five-year, about $3.4B cloud contract in May 2026, served on about $1.6B of Dell servers; with Microsoft's it is a substantial majority of contracted revenue.
against this

NVIDIA is also the sole GPU supplier and holds a right to invest up to $2.1B in IREN shares, so its contract is not an arm's-length test of demand.

current state · 2026-08-27written 2026-10-18
C09facthigh confidence
July's $2.8B of new contracts lifted the year-end run-rate target from $3.7B to over $4B, about 85% then signed, at about 45% prepaid over a four-year average term, for customers from Microsoft and NVIDIA to Perplexity, Figure AI and Together AI.
current state · 2026-07-20written 2026-10-18
C10factmedium confidence
IREN announced a contract with an unnamed frontier AI lab in August; an outside report named Anthropic in October, and neither company has confirmed it.
current state · 2026-10-13written 2026-10-18
04

The results

The numbers

Is it growing?Fast

Sales grew 41% in the year to Jun 2026, slower than the 168% in the year before.

Jun 2023: $75.5MJun 2024: $187MJun 2025: $501MJun 2026: $707M$75.5M$707M
Is it profitable?Losing

Operating margin is −148%, up from −208% in the year to Jun 2023.

Jun 2023: −208%Jun 2024: −15%Jun 2025: 3.5%Jun 2026: −148%−208%−148%
Does growth pay off?Costly

Running costs take 217¢ of each sales dollar, down from 256¢ in the year to Jun 2023.

Jun 2023: 256¢Jun 2024: 68¢Jun 2025: 65¢Jun 2026: 217¢256¢217¢
Does it earn good returns?Poor

Shareholders' money lost 23% a year, up from −56% in the year to Jun 2023.

Jun 2023: −56%Jun 2024: −4.1%Jun 2025: 6.0%Jun 2026: −23%−56%−23%
How long can it keep going?Long runway

It used $898M of cash in the latest year, so the $5.90B it holds lasts about 6.6 years at that pace.

Jun 2023: −$110MJun 2024: −$89.6MJun 2025: −$328MJun 2026: −$898M−$110M−$898M
Is the balance sheet safe?Light debt

It owes $1.70B more than the cash it holds, about 0.8 years of the cash its operations bring in.

Jun 2025: −$398MJun 2026: −$1.70B−$398M−$1.70B
Are shares being diluted?Diluting

The share count rose 477% in 3.0 years, and pay in shares costs 29% of sales.

Jun 2023: 54.8MJun 2024: 99.6MJun 2025: 223MJun 2026: 316M54.8M316M
All the numbers

Filed figures from the company's 10-K and 10-Q, read 2026-10-18. Fiscal years end in June.

Jun 2023Jun 2024Jun 2025Jun 2026
Size and growth
Sales$75.5M$187M$501M$707M
Sales growth-+148%+168%+41%
Profit
Gross margin48%53%68%69%
Operating margin−208%−15%3.5%−148%
Net margin−228%−15%17%−99%
What growth costs, per sales dollar
Sales and marketing0.9%1.1%0.6%2.9%
Pay in shares19%13%8.5%29%
Capital spending154%76%114%424%
Cash
Cash from operations$5.73M$52.2M$246M$2.10B
Free cash flow−$110M−$89.6M−$328M−$898M
Balance sheet
Cash and short-term investments-$411M$565M$5.90B
Debt--$963M$7.59B
Net cash--−$398M−$1.70B
Returns and shares
Return on capital--0.8%-
Shares (diluted)54.8M99.6M223M316M

What growth costs

Growth is making the company less profitable for now. Overhead, much of it pay in shares, rose far faster than sales as staff nearly tripled ahead of the revenue. The bigger cost is building: spending on halls and chips ran at several times sales, and as that equipment switches on, depreciation will climb with it.

The evidence under this - 3 claims
C48facthigh confidence
Overhead grew faster than sales in FY26: SG&A rose to 64% of revenue from 27%, share-based pay to 29% from 9%, and capital spending including hardware to about six times revenue.
historical · FY2026 against FY2025written 2026-10-18
C16facthigh confidence
FY26 SG&A was $449.1M against $136.5M a year earlier, including $205.0M of share-based pay against $42.6M, and depreciation was $417.7M.
historical · FY2026written 2026-10-18
C44facthigh confidence
Headcount was 685 at June 30, 2026, up 166%, plus about 580 from Mirantis in August; management expects similar growth in FY27 and September-quarter cash SG&A up $40M to $50M.
current state · 2026-08-27written 2026-10-18

The last report (27 Aug)

Quarter ended June 2026, filed figures.

-27%
Sales growth
against the same quarter a year earlier
-5.2%
Growth from the quarter before
against -21.6% the quarter before that
-452¢
Operating profit
per dollar of sales

In the year to June 2026 IREN's revenue rose 41% to $707.0M, but the mix is what mattered: AI rentals grew from $16.4M to $128.8M, while mining, still most of the total, began shutting down. In the June quarter alone revenue fell from a year earlier as miners were switched off before the chips arrived.

It lost $702.6M for the year, mostly by writing down retired mining machines. Cash from operations was $2.10B, almost all of it customers paying in advance, against more than $4B spent on buildings and chips.

What it did to the thesisIt proved the switch is real: the AI business is growing fast and customers are paying in advance. It also showed the cost: heavy write-downs, spending far above the cash coming in, and a plan for next year far larger than the company. The view stays Neutral.

The quarter in detail

Sales growth from the previous quarter, filed figures.

Earnings per share $-1.89 against $-0.55 expected.

The evidence under this - 4 claims
C02facthigh confidence
FY26 revenue was $707.0M: AI Cloud $128.8M, up from $16.4M, and bitcoin mining $578.2M.
against this

AI Cloud was still 18% of the year's revenue; the fourth quarter's $70.5M was the first quarter it approached half.

historical · FY2026 (year to June 30, 2026)written 2026-10-18
C15facthigh confidence
FY26 net loss was $702.6M after $638.8M of impairments, mostly mining hardware, and an operating loss of $1,046.7M; adjusted EBITDA fell to $245.7M from $269.7M.
against this

A $558.5M unrealised gain on financial instruments sits below the operating line, so the net loss understates the operating one.

historical · FY2026written 2026-10-18
C17facthigh confidence
FY26 operating cash flow of $2,100.4M included $1,841.7M of customer prepayments; capital spending was $2,998.0M on property plus $1,335.1M on computer hardware.
historical · FY2026written 2026-10-18
C49facthigh confidence
The June 2026 quarter's revenue was $137.2M, AI Cloud $70.5M, with a net loss of $684.0M and adjusted EBITDA of $19.2M as miners were switched off ahead of GPUs.
historical · Q4 FY2026written 2026-10-18
What management did with the money

Last year IREN raised money mostly by selling new shares and convertible bonds, spent $1.63B retiring older convertibles, and bought Mirantis, a software firm, mostly with shares. It pays no dividend and buys back no shares.

Insiders in 2026Q3: 9 purchases and 0 sales, from their Form 4 filings.

The evidence under this - 3 claims
C22facthigh confidence
Diluted shares rose 40.8% in the year to June 2026; IREN raised $4,742.8M in shares and $6,299.6M in convertibles in FY26, and had 394.1M shares at August 14.
against this

Part of the share issuance retired older convertibles in December 2025, at a cost of $1,632.4M, so not all of it was new money.

historical · FY2026written 2026-10-18
C23facthigh confidence
IREN closed the purchase of Mirantis, a cloud software firm with about 580 staff and more than 1,500 enterprise customers, on August 3, 2026, for about $544M paid mostly in 12.6M new shares.
historical · August 2026written 2026-10-18
C21facthigh confidence
Convertible notes total about $6.3B in the 2031 to 2033 series, convertible at $51.40 to $85.63, plus small 2029 and 2030 remnants convertible at $13.64 and $16.81.
current state · 2026-06-30written 2026-10-18
05

The price, and where we disagree

In short. Fair. Buyers pay roughly for the contracts already signed being delivered, and little for the 2027 build, which the market treats as a cost to shareholders.

Share price
$26.99
close,
Company value for each $1 of sales
17.8
rivals' middle 9.9 · its 6-year normal 5.8

The shares have fallen about 60% in a year while revenue per share stood still, and they fell by a fifth in three days in October after a research firm warned that most neoclouds may not survive as independent businesses.

The next tests are close. Results on November 5 should show whether $4B of rentals is still on track and how the build is being paid for; Microsoft's remaining three halls are due by December.

The evidence under this - 4 claims
C25facthigh confidence
Over the 252 sessions to October 16, 2026 the shares fell 60.3% to $26.99 while revenue per share was flat: shares rose 40.8% and the sales multiple fell 60.4%.
historical · 2025-10-15 to 2026-10-16written 2026-10-18
C39factmedium confidence
On October 14 Gartner warned that more than 80% of neocloud providers could cease operating independently by 2030; IREN fell to a 52-week low the next day as CoreWeave's high-yield bonds yielded near 15%.
current state · 2026-10-15written 2026-10-18
C05management claimmedium confidence
IREN says $4B of yearly revenue run-rate is contracted for capacity due in 2026, of which about $1B was billing in late August; it targets more than $4B by the end of the December quarter.
against this
  • Only the Microsoft and NVIDIA contract totals are in the 10-K; the rest of the $4B rests on the company's own count, and no counterparty has disclosed its contract.
  • Management said most of the new revenue shows in the March 2027 quarter, so the December quarter will report little of it.
current state · 2026-08-27written 2026-10-18
C07facthigh confidence
Microsoft's five-year, about $9.7B agreement covers four 50 MW liquid-cooled tranches at Childress; Horizons 2 to 4 are due in the December 2026 quarter with grace periods to early Q2 2027, and Microsoft may end a late tranche.
against this

Horizon 1 itself was late, delayed by NVIDIA component shortages, and if a funded tranche ends without a new customer IREN guarantees that tranche's GPU debt.

current state · 2026-08-27written 2026-10-18
The betSpeculation
If it works
2.3×
from today's value, at the stated multiple
If it fails
keep up to 55%
of today's market value: at most, with what is left counted at book value
How we read the multiple

Trailing sales are mostly a bitcoin business being shut down, so the better measure is what the signed contracts are worth.

On that measure the price is low, but what it leaves out is the cost of the next build, which is larger than the company itself.

  1. The company, debts included, is valued at about $12.6B.
  2. That is about 3.1 times the $4B a year of rentals signed for 2026.
  3. Analysts expect revenue of $7.28B in the year to June 2028.
  4. Next year's building plan alone costs $25B to $30B.

Against its own history. Much dearer on past sales than its own normal, because those sales came from bitcoin mining; the rentals it is now selling are a different business.

The evidence under this - 4 claims
C29estimatemedium confidence
At $26.99 on about 393.5M shares the market value is $10.6B and the vendor's company value $12.6B: about 3.1 times the more than $4B of run-rate contracted for 2026, and 17.8 times trailing sales.
derivedthe pack's market value and company value (S23), divided by the $4B contracted run-rate in C05 and by FY26 revenue in C02
against this
  • The company value uses June 30 net debt; September-quarter spending will have raised it.
  • About $3B of the $4B was not yet billing, so the multiple on revenue actually earned is far higher.
current state · 2026-10-16written 2026-10-18
C30inferencemedium confidence
The price pays for the 2026 contracts and treats the 2027 build mostly as a funding risk: at about 3 times contracted run-rate against Nebius's roughly 9 times its own, the market expects the next gigawatt to cost shareholders.
derivedC29's 3.1 times against the cohort's 9.9 times trailing median (C31) and Nebius's 9 times guided run-rate; the FY27 capex in C19 is more than twice the market value, and the 41% share growth in C22 shows who paid for the last year
against this
  • Nebius's run-rate is mostly billing already, while three quarters of IREN's $4B is still to be delivered, so part of the discount is delivery risk rather than funding.
  • Analysts' $7.28B for fiscal 2028 at the cohort's lowest multiple would be worth more than twice today's company value, so the price may assume less than the plan.
forwardwritten 2026-10-18
C28factmedium confidence
Analysts' average forecasts put revenue at $2.72B for the year to June 2027, $7.28B for 2028 and $13.2B for 2029, the later years from a panel of about four, against $707.0M filed for FY2026.
against this

Four analysts is a thin base, and the 2028 figure needs about 550 MW of IT load billing, more than the 300 MW due in 2026.

forwardwritten 2026-10-18
C19management claimhigh confidence
Management guides FY27 capital spending of about $25B to $30B, against about $14B of cash, committed GPU financing and prepayments, a further $8B of GPU financing and prepayments targeted, and the rest from data-centre financing, operating cash and corporate sources.
against this
  • The rest, roughly $3B to $8B, has no named source, and corporate sources include new shares and convertibles.
  • The data centres are all unencumbered today, so asset finance against them could fill much of the gap without equity.
forwardwritten 2026-10-18
Priced against its rivals

The competitors its own annual report names, each confirmed against the rival's filing. Measured on company value for each $1 of sales, cheapest first:

TickerCompanycompany value for each $1 of sales
AMZNAmazon.com3.7×
ORCLOracle7.1×
GOOGLAlphabet9.4×
CRWVCoreWeave10.4×
MSFTMicrosoft12.2×
IRENIREN Limited17.8×
NBISNebius Group30.8×

The middle of the other 6 is 9.9. IREN Limited is 2nd dearest of 7.

Rivals' figures come from a data provider, so read the spread of the group rather than any single pair.

Dearer than most rivals on past sales, but that measure reads the mining business; on signed rentals it is among the cheapest of the specialists.

Private or foreign rivals that cannot be priced: Crusoe, Lambda, Nscale, SpaceX.

The bet: what it pays if it works

If it works, the shares could be worth about twice today's. The best case we can defend is the revenue analysts expect for the year to June 2028: this year's contracts plus about half of next year's build, rented at recent prices and valued like the cheaper clouds, before the new shares the build may need.

If it fails, with the build stalled and money hard to raise, shareholders keep the contracts already signed, less the debt that built them: at most about half of today's value.

Revenue in two to three yearsMegawatts of IT load billing neededAt the stated multiple
$2.00Babout 150 at 100% kept0.6×
$7.28B (the big win)about 547 at 100% kept2.3×
$13.20Babout 992 at 100% kept4.2×

To pay 2× (a Fair bet) it would need about $6.28B of revenue (about 472 megawatts of IT load billing); to pay 5× (a Cheap bet), about $15.71B of revenue (about 1.2K megawatts of IT load billing), at the same multiple.

The steps it has to take

  • Done Microsoft and NVIDIA signed: about $9.7B and $3.4B over five years
  • Done Horizon 1 delivered and accepted by Microsoft
  • Done $4B of 2026 run-rate contracted, recent deals above $20M a megawatt
  • In progress Horizons 2 to 4 accepted inside the grace periods due 2027-04
  • In progress More than $4B of run-rate billing by the end of December 2026 due 2027-02
  • In progress FY27 build funded mostly with GPU debt, prepayments and site debt due 2027-06
  • Not started The 0.5 GW of 2027 IT load contracted and delivered due 2027-12
  • Not started Fiscal 2028 revenue near $7.3B due 2028-08
The detail behind the label
Rating
Fair
the big win's payoff against the 2× and 5× lines
Cheap bet at about
≈ $9.86
63% below the price (close, )
The evidence under this - 7 claims
C28factmedium confidence
Analysts' average forecasts put revenue at $2.72B for the year to June 2027, $7.28B for 2028 and $13.2B for 2029, the later years from a panel of about four, against $707.0M filed for FY2026.
against this

Four analysts is a thin base, and the 2028 figure needs about 550 MW of IT load billing, more than the 300 MW due in 2026.

forwardwritten 2026-10-18
C45management claimmedium confidence
Management targets about 300 MW of IT load delivered in 2026 and another 0.5 GW in 2027, about 1.2 GW of gross capacity, with Horizons 2 to 4 in the December quarter.
against this

Horizon 1 slipped on NVIDIA supply, and the 10-K says IREN builds with many separate contractors rather than one fixed-price builder, so no single party bears a delay.

forwardwritten 2026-10-18
C06management claimmedium confidence
Recent three-year contracts price above $20M a year per megawatt of IT load with about a two-year payback, three-year pricing is up about 125% since November, and prepayments fund 45% to 55% of the GPUs.
against this
  • The payback is stated on management's own costs for capacity not yet running; no customer has published a price.
  • The Microsoft contract, the largest, works out near $10M a year per megawatt of its 200 MW, so the blended book is well below the recent-deal figure.
current state · 2026-08-27written 2026-10-18
C05management claimmedium confidence
IREN says $4B of yearly revenue run-rate is contracted for capacity due in 2026, of which about $1B was billing in late August; it targets more than $4B by the end of the December quarter.
against this
  • Only the Microsoft and NVIDIA contract totals are in the 10-K; the rest of the $4B rests on the company's own count, and no counterparty has disclosed its contract.
  • Management said most of the new revenue shows in the March 2027 quarter, so the December quarter will report little of it.
current state · 2026-08-27written 2026-10-18
C31facthigh confidence
On trailing sales the filed cohort puts IREN at 17.8 times against a median of 9.9, from Amazon's 3.7 to Nebius's 30.8.
current state · 2026-10-16written 2026-10-18
C53estimatelow confidence
If the build stalls with the 2026 contracts billing, IREN's net debt would be about $9B once that capacity is paid for, against about $1.9B at June 30.
derivedJune 30 net debt of $1.9B (C18, C29) plus roughly $7B of the FY27 spending tied to 2026 deliveries net of prepayments, funded with GPU debt (C19, C20)
against this

Management has not split the $25B to $30B between 2026 deliveries and 2027 builds, so the $7B is this thesis's figure.

forwardwritten 2026-10-18
C46estimatemedium confidence
Funding the FY27 plan likely needs several billion dollars beyond what is arranged: if half of a $3B to $8B gap came as shares at $26.99, that is about 55M to 150M new shares, 14% to 38% more.
derivedC19's $25B to $30B less $14B in hand and $8B targeted leaves $3B to $8B; half of it in shares at the October 16 close of $26.99 on C29's 393.5M shares
against this

Debt against the unencumbered data centres could fund all of it, and higher prepayments on new deals have exceeded GPU cost before.

forwardwritten 2026-10-18

Where we disagree with the market

The market believes

Analysts see a cheap AI cloud with power and signed demand; since September the market fears it cannot pay for its own growth.

We believe

The 2026 contracts are real and largely paid for; whether shareholders gain after that depends on how the next build is financed.

The bulls look at cheap signed revenue and stop; the bears look at the spending plan and stop. The answer sits in how the building is financed: debt against the data centres, which are unpledged today, costs shareholders little, while new shares at today's price cost them a lot.

Against us: the company has raised about $19B in a year and every contract so far came with large prepayments, so the money may keep coming.

What analysts say, and the evidence
Analysts positive
76%
of 21, 1 Oct
Four months earlier
65%
of 17, 1 Jun
The evidence under this - 5 claims
C29estimatemedium confidence
At $26.99 on about 393.5M shares the market value is $10.6B and the vendor's company value $12.6B: about 3.1 times the more than $4B of run-rate contracted for 2026, and 17.8 times trailing sales.
derivedthe pack's market value and company value (S23), divided by the $4B contracted run-rate in C05 and by FY26 revenue in C02
against this
  • The company value uses June 30 net debt; September-quarter spending will have raised it.
  • About $3B of the $4B was not yet billing, so the multiple on revenue actually earned is far higher.
current state · 2026-10-16written 2026-10-18
C30inferencemedium confidence
The price pays for the 2026 contracts and treats the 2027 build mostly as a funding risk: at about 3 times contracted run-rate against Nebius's roughly 9 times its own, the market expects the next gigawatt to cost shareholders.
derivedC29's 3.1 times against the cohort's 9.9 times trailing median (C31) and Nebius's 9 times guided run-rate; the FY27 capex in C19 is more than twice the market value, and the 41% share growth in C22 shows who paid for the last year
against this
  • Nebius's run-rate is mostly billing already, while three quarters of IREN's $4B is still to be delivered, so part of the discount is delivery risk rather than funding.
  • Analysts' $7.28B for fiscal 2028 at the cohort's lowest multiple would be worth more than twice today's company value, so the price may assume less than the plan.
forwardwritten 2026-10-18
C46estimatemedium confidence
Funding the FY27 plan likely needs several billion dollars beyond what is arranged: if half of a $3B to $8B gap came as shares at $26.99, that is about 55M to 150M new shares, 14% to 38% more.
derivedC19's $25B to $30B less $14B in hand and $8B targeted leaves $3B to $8B; half of it in shares at the October 16 close of $26.99 on C29's 393.5M shares
against this

Debt against the unencumbered data centres could fund all of it, and higher prepayments on new deals have exceeded GPU cost before.

forwardwritten 2026-10-18
C19management claimhigh confidence
Management guides FY27 capital spending of about $25B to $30B, against about $14B of cash, committed GPU financing and prepayments, a further $8B of GPU financing and prepayments targeted, and the rest from data-centre financing, operating cash and corporate sources.
against this
  • The rest, roughly $3B to $8B, has no named source, and corporate sources include new shares and convertibles.
  • The data centres are all unencumbered today, so asset finance against them could fill much of the gap without equity.
forwardwritten 2026-10-18
C26facthigh confidence
Twelve of fifteen analysts in the vendor's snapshot rate it a buy; the series read 76.2% positive of 21 on October 1, against 64.7% of 17 in June, and average targets drifted down 12.3%.
current state · 2026-10-01written 2026-10-18
06

What could go wrong, and how we would know

The risks

  • Paying for the build. Next year's plan costs more than twice the company's value; if the gap is filled with new shares, revenue per share may barely grow again.
  • Microsoft walks from a hall. Three Microsoft halls are due by December; if one is late past its grace period, Microsoft may end it and IREN owes its chip loans.
  • Two customers. Microsoft and NVIDIA are most of what is signed; losing either would cut the contracted business deeply.
  • A poor service reputation. An outside rater ranks its older Canadian sites the industry's worst, which can cost renewals from the smaller labs.
  • Expensive, short loans. The newest chip loans cost 9% and fall due within 30 months, before the contracts or the chips have run their course.
  • Rivals and their own chips. Bigger specialists hold far larger backlogs, and Google's own chips give labs a way to skip NVIDIA rentals altogether.
The evidence under this - 7 claims
C19management claimhigh confidence
Management guides FY27 capital spending of about $25B to $30B, against about $14B of cash, committed GPU financing and prepayments, a further $8B of GPU financing and prepayments targeted, and the rest from data-centre financing, operating cash and corporate sources.
against this
  • The rest, roughly $3B to $8B, has no named source, and corporate sources include new shares and convertibles.
  • The data centres are all unencumbered today, so asset finance against them could fill much of the gap without equity.
forwardwritten 2026-10-18
C46estimatemedium confidence
Funding the FY27 plan likely needs several billion dollars beyond what is arranged: if half of a $3B to $8B gap came as shares at $26.99, that is about 55M to 150M new shares, 14% to 38% more.
derivedC19's $25B to $30B less $14B in hand and $8B targeted leaves $3B to $8B; half of it in shares at the October 16 close of $26.99 on C29's 393.5M shares
against this

Debt against the unencumbered data centres could fund all of it, and higher prepayments on new deals have exceeded GPU cost before.

forwardwritten 2026-10-18
C07facthigh confidence
Microsoft's five-year, about $9.7B agreement covers four 50 MW liquid-cooled tranches at Childress; Horizons 2 to 4 are due in the December 2026 quarter with grace periods to early Q2 2027, and Microsoft may end a late tranche.
against this

Horizon 1 itself was late, delayed by NVIDIA component shortages, and if a funded tranche ends without a new customer IREN guarantees that tranche's GPU debt.

current state · 2026-08-27written 2026-10-18
C08facthigh confidence
NVIDIA signed a five-year, about $3.4B cloud contract in May 2026, served on about $1.6B of Dell servers; with Microsoft's it is a substantial majority of contracted revenue.
against this

NVIDIA is also the sole GPU supplier and holds a right to invest up to $2.1B in IREN shares, so its contract is not an arm's-length test of demand.

current state · 2026-08-27written 2026-10-18
C11facthigh confidence
SemiAnalysis rated IREN's cloud Not Recommended in September 2026, calling its British Columbia capacity the worst site in the industry according to users, while saying Childress and Sweetwater look much better and that its bare-metal rentals meet plenty of demand.
against this
  • Microsoft accepted Horizon 1 at Childress and NVIDIA certified it as an Exemplar Cloud, so the largest buyers' own tests passed where the rating is worst.
  • SemiAnalysis sells consulting to GPU clouds and their buyers; it is independent of IREN but not of the market it rates.
current state · 2026-09-23written 2026-10-18
C20facthigh confidence
GPU debt is cheaper where the buyer is investment grade: $3.6B for the Microsoft GPUs at about 6% to 2031, against $2.4B at a fixed 9% for Mackenzie in August, repaid 30 months after each draw.
current state · 2026-08-27written 2026-10-18
C35facthigh confidence
Anthropic signed for multiple gigawatts of Google TPU capacity from 2027, and Alphabet now sells TPU systems to outside customers.
against this

Anthropic also signed up to $44.6B with Nscale, which rents NVIDIA chips, so the move to TPUs adds a supplier rather than replacing one.

current state · 2026-06-30written 2026-10-18
What we still do not know
  • What price per megawatt the Microsoft and NVIDIA contracts actually carry; no buyer has published its terms.
  • How the $3B to $8B of next year's plan with no named source will be raised, and how much of it in shares.
  • Who the frontier lab is: a report named Anthropic, and neither company has confirmed it.
  • Whether the older Canadian sites have fixed the outages users describe.
The evidence under this - 4 claims
C06management claimmedium confidence
Recent three-year contracts price above $20M a year per megawatt of IT load with about a two-year payback, three-year pricing is up about 125% since November, and prepayments fund 45% to 55% of the GPUs.
against this
  • The payback is stated on management's own costs for capacity not yet running; no customer has published a price.
  • The Microsoft contract, the largest, works out near $10M a year per megawatt of its 200 MW, so the blended book is well below the recent-deal figure.
current state · 2026-08-27written 2026-10-18
C19management claimhigh confidence
Management guides FY27 capital spending of about $25B to $30B, against about $14B of cash, committed GPU financing and prepayments, a further $8B of GPU financing and prepayments targeted, and the rest from data-centre financing, operating cash and corporate sources.
against this
  • The rest, roughly $3B to $8B, has no named source, and corporate sources include new shares and convertibles.
  • The data centres are all unencumbered today, so asset finance against them could fill much of the gap without equity.
forwardwritten 2026-10-18
C10factmedium confidence
IREN announced a contract with an unnamed frontier AI lab in August; an outside report named Anthropic in October, and neither company has confirmed it.
current state · 2026-10-13written 2026-10-18
C11facthigh confidence
SemiAnalysis rated IREN's cloud Not Recommended in September 2026, calling its British Columbia capacity the worst site in the industry according to users, while saying Childress and Sweetwater look much better and that its bare-metal rentals meet plenty of demand.
against this
  • Microsoft accepted Horizon 1 at Childress and NVIDIA certified it as an Exemplar Cloud, so the largest buyers' own tests passed where the rating is worst.
  • SemiAnalysis sells consulting to GPU clouds and their buyers; it is independent of IREN but not of the market it rates.
current state · 2026-09-23written 2026-10-18

What would change our view

  1. Neutral→AttractiveThe build is funded with debt and Microsoft's halls land

    It needs all of:

    • ○New shares issued in the year to June 2027 stay below a tenth of the count, the rest paid with debt on the data centres.checked at the next results, due by 5 Nov
    • ○Microsoft accepts its three remaining halls within the grace periods.watched as it happens
  2. Neutral→UnattractiveA tranche ends or the shares pay for the build

    It needs any of:

    • ○Microsoft ends one of its halls because it arrived late.watched as it happens
    • ○New shares issued in the year to June 2027 exceed a fifth of the count.checked at the next results, due by 5 Nov
    • ○Rentals actually billing at the end of 2026 come to less than $3.5B a year.checked at the next results, due by 5 Nov
We would also be wrong if
  • New contracts for 2027 capacity sign below $15M a year per megawatt.

What is coming

  • 5 November 2026 Q1 FY27 results: Whether contracted run-rate holds above $4B, Horizons 2 to 4 are on schedule, and how much of the FY27 funding gap has been raised and in what form.
Every dated event ahead
  • 5 November 2026 Q1 FY27 results: Whether contracted run-rate holds above $4B, Horizons 2 to 4 are on schedule, and how much of the FY27 funding gap has been raised and in what form.
  • 24 November 2026 2026 annual meeting: Whether shareholders approve buying back the shares held under the convertibles' hedges, and the vote on the directors.
  • 31 December 2026 Horizons 2 to 4 delivered to Microsoft: Whether the remaining three Microsoft tranches are accepted on time, or slip into the grace periods that let Microsoft walk.
  • February 2027 Q2 FY27 results: Whether more than $4B of run-rate is billing at year-end, contracts for 2027 capacity and their price, and the end of mining.
Since we wrote this
Written
18 Oct
Price the thesis read
$26.99
16 Oct
  • 21 OctNewsSpanish 300 MW campus announced; release unreadable, view heldThe release could not be opened; the site was already counted in the thesis, so nothing moved.
  • 18 OctThesis writtenNeutral, medium convictionThe 2026 contracts are real and the price is low on them, but next year's build costs more than twice the market value and nothing yet shows who pays for it.

Also checked 1 time with nothing new to act on.

Sources 25

Where this came from

Sources - 25

Every claim above cites one of these, or states the reasoning that derived it. The quote is frozen at the date it was read: a link can rot, and an agent fetch returns a reading of a page rather than the page. Backs counts the whole claim ledger, so it can name a claim this page does not surface.

  1. S01primarycompany filing2026-08-27
    Item 1 business and sites, the competition section, the Microsoft and NVIDIA contracts and their delivery and termination terms, customer concentration, the segment note, useful lives, property and equipment, the convertible notes and GPU financing notes, subsequent events (Mirantis, the Mackenzie financing), headcount and the regulation of new large loads
    backsC01C02C03C04C07C08C12C16C17C18C20C21C22C23C24C25C44C47C48C50C51
  2. S02primarycompany release2026-08-27
    revenue by segment, net loss, impairments, adjusted EBITDA, the cash-flow statement, the balance sheet, contracted ARR, contract pricing and prepayments, the new GPU financings and the delivery targets
    backsC02C05C06C15C16C17C22C25C28C45C48C49
  3. S03primarytranscript2026-08-27
    IREN FY26 fourth-quarter earnings call transcript (FMP, via scripts/transcript_fetch.py)
    FY27 capex of about $25B to $30B and the funding plan for it, ARR of about $1B today, the delivery targets of about 300 MW of IT load in 2026 and another 0.5 GW in 2027, pricing above $20M per megawatt, 6% and 9% GPU financing, mining switched off by December, headcount and SG&A guidance; analysts named in the handoffs included Goldman Sachs, Macquarie, Cantor, Compass Point, B. Riley, H.C. Wainwright, BTIG and Canaccord
    3-year contract pricing is up about 125% since November, 5-year is up about 70%.
    backsC03C05C06C10C19C20C44C45
  4. S04primarycompany release2026-07-20
    the year-end ARR target raised from $3.7B to more than $4B, about 85% contracted, prepayments near 45%, a weighted average term of about four years, and the named customers
    backsC09
  5. S05primarycompany release2026-08-13
    the first 50 MW liquid-cooled tranche at Childress delivered and accepted, and NVIDIA Exemplar Cloud status on GB300 NVL72
    backsC12
  6. S06primarycompany filing2026-10-13
    the ownership table at September 28, 2026, the B Class shares and their votes, the co-chief executives' Staking Grants, the short-term and performance share plans, the executive biographies, and the November 24, 2026 meeting's proposals
    backsC40C41C42C52
  7. S07primarycompany filing2026-05-19
    about $1.6B of GPU servers bought from Dell to serve the five-year NVIDIA cloud contract
    backsC08
  8. S08primaryindustry data2026-09-23
    IREN rated Not Recommended - Underperforming on its managed cloud at the British Columbia sites; Childress and Sweetwater said to look much better; a recommendation that IREN focus on bare metal, where demand is plentiful. SemiAnalysis sells consulting to clouds and buyers
    The #1 worst site in the industry according to users.
    backsC11
  9. S09primaryindustry data2026-04-02
    the measured size of the specialised AI cloud market in 2025, and a forecast near $400B by 2031 that is not used here
    neocloud revenues are scaling at an unprecedented pace, reaching $9 billion in Q4-up 223% year-over-year-and exceeding $25 billion for full-year 2025
    backsC33
  10. S10primarygovernment data2025-04-10
    data-centre electricity more than doubling to about 945 TWh by 2030; the PDF was read from the IEA's own file host
    Electricity consumption in accelerated servers, which is mainly driven by AI technology adoption (Box 2.1), is projected to grow by 30% annually in the Base Case
    backsC34
  11. S11primaryindustry data2026-10-17
    the index page read 'As of Oct 17, 2026 2.82 USD / GPU-hour', up 6.4% over seven days
    The H100 Rental Price Index (Neo-Cloud ticker SDH100RT) is the Silicon Data benchmark for NVIDIA H100 GPU rental pricing.
    backsC13
  12. S12primarycompany filing2026-08-12
    $103.7B of remaining performance obligations and customer concentration; taken from the Nebius thesis's reading of 2026-10-02, not re-read
    backsC32C37
  13. S13primarycompany release2026-08-11
    an adjusted operating margin of 5% against 16% a year earlier; taken from the Nebius thesis's reading of 2026-10-02
    backsC32
  14. S14primarycompany filing2026-07-29
    $329.1B of datacenter leases not yet commenced and reliance on outside cloud infrastructure; no mention of IREN; taken from the Nebius thesis's reading of 2026-10-02
    backsC36
  15. S15primarycompany filing2026-07-30
    2026 capex guided at $130B to $145B and $349.31B of commitments, mostly third-party cloud capacity; taken from the Nebius thesis's reading
    backsC36
  16. S16primarycompany filing2026-07-24
    the sale of TPU systems to outside customers; taken from the Nebius thesis's reading
    backsC35
  17. S17primarycompany release2026-04-06
    a large AI buyer moving part of its compute to Google's own chips
    We have signed a new agreement with Google and Broadcom for multiple gigawatts of next-generation TPU capacity that we expect to come online starting in 2027.
    backsC35
  18. S18primarycompany filing2026-09-18
    statements of work with Microsoft worth up to about $43.8B and Anthropic agreements up to about $44.6B; taken from the Nebius thesis's reading
    backsC37
  19. S19primarycompany release2026-08-12
    a rival's four Q2 2026 deals priced at $20M to $25M a year per megawatt with prepayments of 50% to 60%; taken from the Nebius thesis's reading of 2026-10-02
    backsC14
  20. S20secondarynews2026-09-08
    the company's September 8 announcement as an outlet reported it; the GlobeNewswire release closes the connection and no filing carries it (scripts/press_fetch.py walked the filing and outlet routes)
    its 2 GW Sweetwater Hub in Texas was conditionally included as Base Load in the Electric Reliability Council of Texas (ERCOT) Batch Zero process
    backsC38
  21. S21secondarynews2026-10-13
    an unconfirmed report naming Anthropic as the undisclosed frontier-lab customer
    Neither IREN nor Anthropic has confirmed the reported contract, leaving shares vulnerable to further drift without a fresh catalyst.
    backsC10
  22. S22secondarynews2026-10-15
    Gartner's warning as reported, the shares at a 52-week low, CoreWeave's high-yield bonds near 15%; Gartner's report itself is paywalled and was not read
    Gartner warned more than 80% of neocloud providers could cease current operations as independent businesses by 2030.
    backsC39
  23. S23primaryvendor data2026-10-18
    Research pack, frozen at content/IREN/research-pack.json
    price, returns, the price-move decomposition, the analyst split and its drift, short interest, consensus revenue estimates, the filed competitor cohort and its multiples
    backsC22C25C26C27C28C31C43
  24. S24primarycompany filing2026-10-18
    Form 4 filings, read via scripts/insider_fetch.py
    nine filings since IREN began filing Form 4 in July 2026, all grants and vestings; no open-market purchase or sale
    backsC43
  25. S25primarycompany filing2026-03-02
    a six-year useful life for computing equipment; taken from the Nebius thesis's reading
    backsC24
Rendered from content/IREN/thesis.json · thesis reviewed 2026-10-21. This page explains a company; it does not say what to pay, when to buy or how much.